Under Construction in Precinct 1
-
US 59/IH 69 (SH 99 to Wharton County line) These dates reflect completion of the project and not necessarily when lanes will be open to traffic. There is typically a month of work (if not more) from when the lanes are open until project completion.
- SH 99 to Reading Road – June 2023
- Remaining Work–Repair high mast lights,Punch list items.
- Remaining Work–Repair high mast lights,Punch list items.
- Reading Road to Spur 10 – June 2023
- Remaining Work – Reconstruct frontage road between FM 2218 and SH 36.
- Remaining Work – Reconstruct frontage road between FM 2218 and SH 36.
- Spur 10 to Darst Road – June 2023
- Remaining Work – Punch list items.
- Remaining Work – Punch list items.
- Darst Road to Wharton County line – June 2023
- Remaining work–Punch list items.
- Remaining work–Punch list items.
- SH 99 to Reading Road – June 2023
-
FM 1463 Widening (IH 10 to FM 1093) (Widen from 2-lane to 6-lane highway north of Spring Green Road and 4-lane south of Spring Green Road with raised medians.)
- Let Date – August 2021
- Est. Cost – $108.4 million
- Est. Completion Date – June 2026
-
FM 2218 (US 59/IH 69 to SH 36) (Widen from 2-lane to 4-lane highway with raised medians)
- Let Date – June 2020
- Est. Cost – $43.6 million
- Est. Completion Date – June 2024
Future Projects in Precinct 1
- FM 723 Widening (Brazos River to FM 1093) (Widen from 2-lane highway to a 4-lane highway with raised medians)
- Let Date – June 2023
- Est. Cost $125.4 million
- SH 99 Widening (FM 1093 to IH10) (Widen from 4-lane highway to 6-lane highway; SB frontage road between Fry Road and FM 1093)
- Let Date – January 2023
- Est. Cost $102.2 million
- IH 10 Widening (Snake Creek to Mason Rd.) ((Widen from 6-lane highway to a 10-lane highway (2 general purpose and 2 diamond))
- Let Date – April 2024
- Est. Cost $140.0 million
- IH 10 Widening (FM 359 to Fort Bend County Line) (Widen from 6-lane highway to a 10-lane highway (2 general purpose and 2 diamond))
- Let Date – November 2024
- Est Cost $238.4 million
- IH 10 Widening (Waller County Line to Snake Creek) ((Widen from 6-lane highway to a 10-lane highway (2 general purpose and 2 diamond))
- Let Date – June 2025
- Est. Cost $78.0 million
- SH 36 Widening (IH 69 to FM 2218) (Widen from 2-lane highway to a 4-lane divided highway)
- Let Date – June 2024
- Est. Cost $45.0 million
- US 90A Widening (FM 359 to SH 99) (Widen from 4-lane highway to 6-lane divided highway)
- Let Date – August 2024
- Est. Cost $34.2 million
- Spur 10 Widening (SH 36 to IH 69) (Widen to 4-lane divided highway)
- Let Date – January 2029
- Est. Cost $35.7 million
- US 90 Widening (IH 10 to FM 1463) (Widen to 4-lane divided highway)
- Let Date – January 2030
- Est. Cost $55.6 million
- US 90A Widening (FM 762 to FM 359) (Widen from 4-lane highway to 6lane divided highway)
- Let Date – March 2030
- Est. Cost $20.0 million
- SH 36 Widening (Austin County Line to SS 529) (Widen to 4-lane divided highway)
- Let Date – January 2035
- Est. Cost $97.3 million *CURRENTLY UNFUNDED*
- FM 359 Widening (FM 1093 to Mason Rd) (Widen to 4-lane divided highway)
- Let Date – January 2035
- Est. Cost $80.0 million *CURRENTLY UNFUNDED*
- FM 1093 Widening (FM 1489 to FM 359) (Widen to 4-lane divided highway)
- Let Date – January 2035
- Est. Cost $70.0 million *CURRENTLY UNFUNDED*
- US 90A Widening (Wharton County Line to SH 36) (Widen to 4-lane divided highway)
- Let Date – August 2024
- Est. Cost $118.0 million *CURRENTLY UNFUNDED*